EPBD and whole-life carbon: what the recast directive asks for and when

What the recast EPBD requires on life-cycle GWP for new buildings: the Article 7 dates, the Annex III calculation framework and the product data needed.

Published 6 min read

In short

The recast EPBD, Directive (EU) 2024/1275, requires the life-cycle global warming potential (GWP) of new buildings to be calculated and disclosed in the energy performance certificate, from 1 January 2028 for new buildings above 1,000 m² of useful floor area and from 1 January 2030 for all new buildings. Member States must publish a roadmap for limit values by 1 January 2027 and set targets for new buildings from 2030. The calculation follows the Union framework in Annex III, as replaced by Delegated Regulation (EU) 2026/52, and is applied through national methods.

Key takeaways

  • Article 7(2): life-cycle GWP is calculated and disclosed in the energy performance certificate from 1 January 2028 for new buildings above 1,000 m², and from 1 January 2030 for all new buildings.
  • Article 7(5): each Member State publishes a roadmap for limit values by 1 January 2027, with targets for new buildings from 2030.
  • Annex III, replaced by Delegated Regulation (EU) 2026/52, fixes a 50-year reference study period, results in kg CO₂eq per m² of useful floor area and the modules to include.
  • Product-specific data to EN 15804, such as an EPD, may be used only where national legislation permits it.
  • As of November 2026 transposition is incomplete, so the method, data and limits must be checked in national law.

What does the EPBD require on whole-life carbon?

The EPBD, recast as Directive (EU) 2024/1275, requires Member States to ensure that the life-cycle global warming potential (GWP) of new buildings is calculated and disclosed in the energy performance certificate of the building (Article 7(2)). It does not set an EU-wide carbon limit. Each Member State has to plan and introduce its own limit values (Article 7(5)).

Life-cycle GWP is the directive's term for what UK practice calls whole-life carbon. Article 2(25) defines it as an indicator that quantifies the contribution of a building to global warming along its full life cycle. Article 2(24) describes that life cycle: the production and transport of construction products, construction-site activities, energy use in the building, the replacement of products, and demolition, waste management, reuse, recycling and final disposal. The indicator therefore covers both embodied carbon and operational emissions.

Two points are often mixed up:

  • The zero-emission building standard that Article 7(1) makes mandatory for new buildings is defined by energy performance and operational emissions (Article 2(2)). Life-cycle GWP is a separate requirement.
  • The 2028 and 2030 obligations are to calculate and disclose. Limits arrive through national law.

From which dates does the Energy Performance of Buildings Directive require this, and for which buildings?

Disclosure of life-cycle GWP starts on 1 January 2028 for new buildings with a useful floor area larger than 1,000 m², and on 1 January 2030 for all new buildings (Article 7(2)).

DateWhat happensLegal basis
28 May 2024The recast directive enters into forceArticle 37
24 May 2026The Union calculation framework (new Annex III) enters into forceDelegated Regulation (EU) 2026/52
29 May 2026Deadline for transposing Article 7 and Annex III into national lawArticle 35(1)
1 January 2027Member States publish a roadmap for limit values and notify it to the CommissionArticle 7(5)
1 January 2028Life-cycle GWP is calculated and disclosed for new buildings above 1,000 m² of useful floor area. New buildings owned by public bodies are zero-emission buildingsArticle 7(2)(a) and 7(1)(a)
1 January 2030Life-cycle GWP is calculated and disclosed for all new buildings. All new buildings are zero-emission buildings. National targets for life-cycle GWP start from 2030Article 7(2)(b), 7(1)(b) and 7(5)

Three qualifications apply:

  • Building permits. Member States may decide not to apply these dates to buildings for which permit applications had already been submitted by then (Article 7(4)).
  • Excluded categories. Buildings that a Member State excludes from the energy performance certificate under Article 20(6) may also be left out of the calculation (recital 1 of Delegated Regulation (EU) 2026/52).
  • Existing buildings. There is no general obligation. Where a Member State defines an A+ energy class, life-cycle GWP must be estimated and disclosed for existing buildings renovated to that class (Article 19(2)).

How is the life-cycle GWP calculated?

It is calculated with a national method that follows the Union framework in Annex III. The Commission replaced the original Annex III through Delegated Regulation (EU) 2026/52, adopted on 16 December 2025 under Article 7(3) and published in the Official Journal on 4 May 2026.

The framework fixes these points:

  • Standard. The calculation follows the relevant parts of EN 15978:2011 and takes into account any subsequent standard. The annex adds that this does not codify the standard in law. CEN published a revised edition, EN 15978:2026, in spring 2026.
  • Reference study period. 50 years. This is a convention for comparability, not an assumed service life.
  • Unit. kg CO₂eq per m² of useful floor area. Each Member State sets out how that area is measured.
  • Timing. The figure in the energy performance certificate reflects the as-built stage. The recitals of the delegated regulation add that it should already be calculated or estimated at design stage, while the design can still change.
  • Life-cycle stages. Modules A1–A5, B1–B4, B6, C1–C4, D1 and D2 are required. B5, B7 and B8 are optional. For several modules, including A4, B1–B3, C1–C4 and D1, a Member State may limit the calculation to information available at product level and to generic or default values.
  • Building scope. At least the shell and core: substructure, structure, external architectural works such as façade and roof, internal non-structural works, and building services and equipment. External works are optional.
  • Reporting. GWP-total is shown at least per stage: A1–A3, A4–A5, B1–B4, B6, C1–C4, D1 and D2.

What each module covers is explained in EN 15804 and EN 15978 explained.

What must Member States do, and by when?

Member States had to transpose Article 7 and Annex III by 29 May 2026, and they must publish their roadmap for limit values by 1 January 2027.

The roadmap details how limit values on the total cumulative life-cycle GWP of all new buildings will be introduced. It sets targets for new buildings from 2030 on a progressive downward trend, with maximum limit values for different climatic zones and building typologies (Article 7(5)). The Commission's guidance notice (C/2025/6438, Annex 13) reads this as follows: the roadmap need not contain numerical values, but the first limit values must be in force by 1 January 2030 at the latest.

Annex III leaves several choices to national rules:

  • how useful floor area is defined;
  • which optional modules are included, and where default scenarios are allowed;
  • how the number of replacements in module B4 is counted;
  • how the embodied emissions of on-site energy generation are allocated, using one of three approaches;
  • which generic data and default values apply. Member States must make these publicly available, so that a calculation is possible without product-specific data.

When a building is checked against a limit value, a Member State may also leave out parts of the life-cycle stages or of the building components. The figure that is disclosed and the figure that is regulated can therefore differ.

Where this stands, as of November 2026. Transposition is incomplete. On 15 July 2026 the Commission opened infringement procedures by sending letters of formal notice to all 27 Member States for failing to fully transpose the directive. National starting points differ as well. The Commission's guidance records that some Member States regulated life-cycle GWP before the directive: France put limit values in place in 2022, and Denmark introduced a limit value for new buildings over 1,000 m² in 2023. This article describes the EU framework only. The method, the accepted data, the default values and any limits have to be checked in the national law that applies to the project.

Which product data does a whole-life carbon assessment need?

A whole-life carbon assessment needs, for each product or material, the GWP per life-cycle module and the unit it refers to, taken from the type of data that the national method ranks highest.

Annex III sets an order of preference:

Data typeStatus in Annex III
Data from declarations of performance and conformity under the Construction Products RegulationMust be used when available
Compatible data under ecodesign and energy labelling legislationMust also be used
Product-specific or project-specific data calculated to EN 15804 or EN 50693Only where national legislation specifically permits it. Member States are encouraged to allow it
Average data for a product groupOnly where national legislation specifically permits it
Generic data and default valuesSet by Member States on conservative assumptions, to fill gaps

The third row is where an environmental product declaration (EPD) sits (see what is an EPD). The first row will fill gradually. Regulation (EU) 2024/3110 requires declarations drawn up under it to cover climate change effects from 8 January 2026 (Article 15(3)), but harmonised standards cited under the previous regulation remain valid until they are withdrawn (Article 95(3)). Product families therefore move across as their standards are replaced.

For each product in the bill of quantities, record:

  1. the product, the manufacturer and the document reference;
  2. the declared unit;
  3. GWP-total for each declared module, kept separate (see GWP by life-cycle module);
  4. the version of EN 15804 the declaration follows;
  5. the validity dates.

An assistant connected to Quarry returns the GWP per module as printed in the EPD, the validity dates and the document itself. Whether that type of data is accepted under the national method, and the assessment as a whole, remain the responsibility of the assessor.

Questions people ask

Sources

  1. Directive (EU) 2024/1275 of the European Parliament and of the Council of 24 April 2024 on the energy performance of buildings (recast) · Official Journal of the European Union, EUR-Lex
  2. Commission Delegated Regulation (EU) 2026/52 of 16 December 2025 amending Annex III to Directive (EU) 2024/1275 as regards the Union framework for the national calculation of life-cycle global warming potential · Official Journal of the European Union, EUR-Lex
  3. Commission Notice C/2025/6438 providing guidance on new or substantially modified provisions of the recast Energy Performance of Buildings Directive, Annex 13: Life-cycle global warming potential of new buildings · Official Journal of the European Union, EUR-Lex
  4. Energy Performance of Buildings Directive · European Commission, Directorate-General for Energy
  5. Global warming potential of buildings · European Commission, Directorate-General for Energy
  6. The Commission calls on EU countries to transpose the reinforced rules on the energy performance of buildings (15 July 2026) · European Commission, Directorate-General for Energy
  7. Regulation (EU) 2024/3110 of the European Parliament and of the Council of 27 November 2024 laying down harmonised rules for the marketing of construction products · Official Journal of the European Union, EUR-Lex
  8. EN 15978:2026 - A Harmonized Method to Assess the Environmental Performance of Buildings · CEN-CENELEC
  9. Whole life carbon assessment for the built environment, RICS professional standard, 2nd edition (version 3, August 2024) · Royal Institution of Chartered Surveyors

More from the blog

ai for architects

AI for architects: asking about materials and getting a cited source

How AI for architects handles material questions: why a connected assistant can cite the EPD behind a carbon figure, and what you still check yourself.

7 min read

embodied carbon

Embodied carbon explained: what it is and how it is calculated

Embodied carbon is the greenhouse gas emitted to make, install, maintain and dispose of building materials. How it is defined, calculated and sourced.

6 min read

en 15804

EN 15804+A2 and EN 15978 explained for people who use EPDs

What EN 15804 requires of an EPD, what changed from +A1 to +A2, why the two are not comparable, and how EN 15978 uses EPD data in a building LCA.

7 min read