Embodied carbon explained: what it is and how it is calculated
Embodied carbon is the greenhouse gas emitted to make, install, maintain and dispose of building materials. How it is defined, calculated and sourced.
Published 6 min read
In short
Embodied carbon is the greenhouse gas emitted to make, transport, install, maintain, replace and finally dispose of the materials in a building, as opposed to the operational carbon from the energy the building uses. It is calculated by multiplying the quantity of each product by its global warming potential (GWP) per unit for each life-cycle module, then adding the results across the building. The per-unit figures come from environmental product declarations (EPDs) or, where none exists, from generic or default data.
Key takeaways
- Embodied carbon covers the material-related life-cycle modules A1–A5, B1–B5 and C1–C4, in kg CO₂e.
- Operational carbon covers energy and water used in operation, modules B6 and B7.
- The calculation is quantity multiplied by GWP per declared unit, module by module, added up over the building.
- Per-unit figures come from EPDs first, then from generic data and default values.
- Module D is reported separately and is not part of the embodied carbon total.
What is embodied carbon in construction?
Embodied carbon is the greenhouse gas emitted, and removed, in connection with the materials and construction processes of a building over its whole life. That means making the products, transporting and installing them, maintaining and replacing them, and dealing with them at the end of life. It is expressed in kilograms of CO₂ equivalent (kg CO₂e).
This wording follows the RICS professional standard on whole-life carbon assessment, which ties the term to the life-cycle modules of EN 15978:
| Stage | Modules | What is counted |
|---|---|---|
| Product | A1–A3 | Raw material supply, transport to the factory, manufacturing |
| Construction process | A4–A5 | Transport to site, installation |
| Use, material-related | B1–B5 | Use, maintenance, repair, replacement, refurbishment |
| End of life | C1–C4 | Deconstruction, transport, waste processing, disposal |
RICS also lists a module A0 for pre-construction activities, which it assumes to be zero for buildings.
Two related terms are worth fixing at the start:
- Upfront carbon is the part emitted up to practical completion, modules A1–A5. RICS excludes the biogenic carbon stored in installed products from this figure and reports it separately.
- Module D reports benefits and loads beyond the system boundary, such as the potential for reuse and recycling. It is shown separately and is not part of the embodied carbon total.
The scale is large. The Global Status Report for Buildings and Construction 2025–2026 cites an International Energy Agency estimate that cement, steel and aluminium used in buildings alone accounted for about 2.1 Gt CO₂ in 2024, or 9% of global emissions. That figure covers three materials only.
What is the difference between embodied carbon and operational carbon?
Operational carbon comes from the energy and water a building consumes in use. Embodied carbon comes from its materials and construction. Whole-life carbon is the two together, with module D reported alongside.
| Embodied carbon | Operational carbon | |
|---|---|---|
| Source | Materials and construction processes | Energy and water consumed in use |
| Modules | A1–A5, B1–B5, C1–C4 | B6, B7 |
| When it occurs | Before handover, then at each replacement and at end of life | Every year of operation |
| Main input data | Material quantities and product data such as EPDs | Energy calculation and emission factors |
The same report puts operational emissions from buildings at 9.9 Gt CO₂ in 2024 and calls them the largest and best-tracked part of the life-cycle impact of buildings. Embodied emissions are less consistently reported, because they span many materials and many life-cycle stages.
Timing is the practical difference. Operational carbon can still be reduced after handover, for example by changing the energy supply. Upfront emissions cannot. The European Commission's guidance on the recast Energy Performance of Buildings Directive makes the same point: once a product has been built in, its emissions have already occurred, so the calculation has to be made before construction starts.
EU law uses neither term as its headline. The directive speaks of life-cycle GWP, an indicator that brings together the emissions embodied in construction products with those from the use stage. See EPBD and whole-life carbon for the dates and duties.
Is embodied energy the same thing?
No. Embodied energy counts the same life-cycle stages in units of energy, usually megajoules. Embodied carbon counts greenhouse gas emissions.
The two diverge wherever emissions do not come from burning fuel. Cement is the clearest case. According to the Joint Research Centre of the European Commission, the calcination reaction in clinker production releases 526 kg of CO₂ per tonne of clinker, while fuel for the kiln adds 282 kg per tonne on the EU average. An energy figure captures only the second part.
The two are treated as separate quantities in research as well, for example in the Annex 57 project of the IEA Energy in Buildings and Communities Programme on embodied energy and CO₂-equivalent emissions. EU building rules are written in kg CO₂e. Embodied energy remains useful as a measure of resource use, but it is not a substitute.
How is embodied carbon calculated for a building?
Multiply the quantity of each product by its global warming potential (GWP) per unit, module by module, and add the results across the building.
- Take quantities from the model or the bill of quantities, element by element.
- Convert each quantity into the declared unit of the product data, such as m³, tonne or m².
- Multiply by the GWP per declared unit for each module that the data declares.
- For products that will be replaced within the study period, add the replacements (module B4).
- Add up all products, keep the modules separate, and keep module D apart.
- Divide by floor area to obtain kg CO₂e per m².
A worked example: a floor slab needs 400 m³ of C32/40 concrete. Suppose the EPD of the specified mix declares 256 kg CO₂e per m³ for modules A1–A3, which is the median of the 2026 UK market benchmark for that strength class. The product stage of that concrete then contributes 400 × 256 = 102,400 kg CO₂e, or about 102 t CO₂e. The same step is repeated for the other modules and for every other product. The quantity is hypothetical, and a real calculation uses the figure from the EPD of the product actually specified.
The European method for the building-level calculation is EN 15978, whose current edition was published by CEN in 2026. It consolidates the data from EPDs and their information modules under EN 15804+A2. EN 15804 itself states that EPD information is expressed so that it can be added up for a building, and that the rules for doing so sit elsewhere. The two standards are compared in EN 15804 and EN 15978 explained.
For new buildings in the EU, Annex III of the Energy Performance of Buildings Directive adds fixed conventions: a reference study period of 50 years and results per m² of useful floor area.
Where do the numbers come from?
The per-unit figures come from environmental product declarations where they exist, and from generic or default data where they do not.
An EPD is a Type III environmental declaration under ISO 14025, presenting quantified environmental information on the life cycle of a product. For construction products it follows EN 15804, which defines the indicators, the life-cycle modules and the declared unit, and contains a clause on verification and validity. The result is a table of GWP per module for one declared unit. What is an EPD and GWP by life-cycle module cover the document and the table.
EPDs are published in the registries of programme operators, in national databases and on manufacturers' websites.
The EU framework ranks the data types. Product data issued under the Construction Products Regulation comes first. Product-specific data calculated to EN 15804 follows where national legislation permits it, then averages for a product group, generic data and default values. Member States may set default values on conservative assumptions, to encourage the use of specific data.
An assistant connected to Quarry returns the GWP per module exactly as printed in the EPD, without summing modules or estimating, together with the validity dates and the document. How to connect an assistant is described separately. The quantities, the scenarios and the assessment remain the work of the professional.
What does an embodied carbon calculator do?
An embodied carbon calculator automates the arithmetic above. It holds a library of GWP factors, takes quantities from the user or from a model, and multiplies.
Two calculators give different answers for the same building when their libraries, modules or building scope differ. Before relying on a result, check:
- which life-cycle modules are included;
- whether the factors are product-specific EPDs, averages or generic values;
- whether the underlying EPDs are still valid;
- which building elements are counted;
- the reference study period and the floor area used.
The same checks apply when two products are compared, as set out in sustainable building materials: how to compare them with EPD data. For cement and steel, which the Global Status Report names as the dominant drivers of embodied emissions in new buildings, see low-carbon concrete and steel.
Questions people ask
Sources
- Whole life carbon assessment for the built environment, RICS professional standard, 2nd edition (version 3, August 2024) · Royal Institution of Chartered Surveyors
- Directive (EU) 2024/1275 of the European Parliament and of the Council of 24 April 2024 on the energy performance of buildings (recast) · Official Journal of the European Union, EUR-Lex
- Commission Delegated Regulation (EU) 2026/52 of 16 December 2025 amending Annex III to Directive (EU) 2024/1275 as regards the Union framework for the national calculation of life-cycle global warming potential · Official Journal of the European Union, EUR-Lex
- Commission Notice C/2025/6438 providing guidance on new or substantially modified provisions of the recast Energy Performance of Buildings Directive, Annex 13: Life-cycle global warming potential of new buildings · Official Journal of the European Union, EUR-Lex
- Global Status Report for Buildings and Construction 2025–2026 · United Nations Environment Programme and Global Alliance for Buildings and Construction
- EN 15804:2012+A2:2019 Sustainability of construction works - Environmental product declarations - Core rules for the product category of construction products (official preview: contents, introduction and scope) · Slovak Office of Standards, Metrology and Testing (ÚNMS SR)
- EN 15978:2026 - A Harmonized Method to Assess the Environmental Performance of Buildings · CEN-CENELEC
- EVS-EN ISO 14025:2010 Environmental labels and declarations - Type III environmental declarations - Principles and procedures (ISO 14025:2006) · Estonian Centre for Standardisation and Accreditation (EVS)
- Mapping the transition of the EU cement industry to carbon neutrality, Science for Policy Brief JRC144123 (2026) · European Commission, Joint Research Centre
- EBC Annex 57: Evaluation of Embodied Energy and CO2 Equivalent Emissions for Building Construction · IEA Energy in Buildings and Communities Programme
- LCCG Market Benchmark for the embodied carbon of concrete, 2026 update (spreadsheet version 5.0) · MPA The Concrete Centre on behalf of the Low Carbon Concrete Group